Primers + Mesh
Surface Prep
Before you prime and mesh it’s essential that your surface is completely flat, dry and well consolidated, so that there is no chance of movement. Use a small amount of the base coat or a suitable filler to flush out joins and counter-sunk screw holes, then sand until the surface is completely flat. See surface prep for full details of preparing surface for microcement.
Applying Primer 100 & Fibreglass Mesh
Fibreglass mesh adds strength to your microcement and adds strength to the substrate. Cut the mesh to size & then flip it over so that it curls towards the surface. You might find it easier to use Self Adhesive Fibreglass Mesh on corners.
Use a medium pile roller to apply an even coat of primer to the surface and mesh. The primer should help to hold the mesh in place, but you can also use stainless steel staples to hold it down.
Try to get the mesh flat to the surface. If you do get bubbles in the mesh that you can’t flatten, you might need to move on and deal with them when applying base coats by slashing the bubble with your trowel or utility knife and flattening down at that point. If bubbles in the mesh are still showing through after the 2nd base coat, sand them out so that you have a completely flat surface before applying top coats.
Primer 100 is a thick, high-quality product. To get the full consumption out of the bottle, you may need a little water. Add up to 10% water & shake to get all of the primer out of the container.
Fresh Plaster & Concrete
On freshly laid concrete, screed, self-leveller or fresh plaster use Primer 100 mixed with water at a ratio of 50:50 before applying a neat coat. Similar to a mist coat of paint, this will prevent the primer from sitting on the surface and create a strong bond between surface and microcement. The primer needs to sink into the substrate to take hold, which is where the water comes in.
After around 1 hour it should be dry enough to take a neat coat of Primer 100. If the substrate is very absorbent, you might need to buy more primer to complete this stage.
Leave to Dry
Leave the primer to dry. This should take around 1 hour. Primer 100 will loose it’s tack after 8 hours, so you will need to make sure you apply your base coat within 8 hours or apply another coat of re-prime.
When to Choose High Performance Primer
We highly recommend that you choose this option if you are working on load-bearing horizontal surfaces that have joins e.g. OSB/Ply/MDF/Cement Board flooring or across transitions between shower trays and surrounding floors. It also helps to strengthen concrete surfaces that have cracked, however the cracks should be repaired in advance. It’s also useful for bridging joins between boards in furniture and worktops.
This primer helps to inhibit moisture and stains from transferring through from your substrate.
If you think you need High Performance Primer but haven’t got it in your kit, the products are also available to buy separately.
Cemher Primer 100
Highly Absorbent Surfaces e.g. Fresh Plaster / Screeds All Other Surfaces including Non Absorbent Surfaces Process Highly Absorbent Surfaces e.g. Fresh Plaster / Screeds: Diluted Coat followed by Neat Coat All Other Surfaces including Non Absorbent Surfaces: Apply Neat Coat Directly Mix Ratio Highly Absorbent Surfaces e.g. Fresh Plaster / Screeds: Diluted Coat:
50% Water / 50% Primer 100
Neat Coat:
Maximum 10% WaterAll Other Surfaces including Non Absorbent Surfaces: Maximum 10% Water Standard Consumption Highly Absorbent Surfaces e.g. Fresh Plaster / Screeds: 1l per 4 - 6m2 All Other Surfaces including Non Absorbent Surfaces: 1l per 8 - 10m2 Estimated Drying Time Highly Absorbent Surfaces e.g. Fresh Plaster / Screeds: Diluted Coat:
30 minutes
No Maximum
Neat Coat:
Minimum 30 minutes
Maximum 8 hoursAll Other Surfaces including Non Absorbent Surfaces: Minimum 30 minutes
Maximum 12 hoursTools Required Highly Absorbent Surfaces e.g. Fresh Plaster / Screeds: Medium Microfibre Roller
Roller Tray
PPEAll Other Surfaces including Non Absorbent Surfaces: Medium Microfibre Roller
Roller Tray
PPE -
Base Coats
Mixing 1st Coat of Microne Base without Colour
And it’s not essential that you add colour to the 1st base coat, but you may have enough colour toners to do so if your order requires a tub to be split between the 1st and 2nd base coat.
To loosen the mix, mix thoroughly with a microcement mixer head attachment on a cordless drill. If it still feels stiff, you can add up to 10% water to loosen & mix further. That’s a maximum of 1l per 10kg.
Let the mixture rest for a few minutes before applying.
Applying the Microne Base
Using a Microcement Trowel, work your way out from one corner creating a random edge pattern. Keep trowel movements small and random, avoid long sweeping arches – as these will show through to your final finish.
Use the grain in the microcement as your level – if you apply the microcement thicker than the size of the grain, the finish won’t be as strong and will require a lot more sanding. Run the trowel back over each section that you have put down to smooth it out and remove excess product. You should still be able to see the mesh after after applying this coat.
Completely coat each surface without stopping. For complete rooms, start with ceilings, then walls from left to right (or right to left) and then the floor.
Run your finger or a corner trowel along internal corners to push the microcement into the corner and then gently trowel away the excess product.
Mixing 2nd Coat of Microne Base
Add 1 x colour toner for Microne Base to the tub and mix thoroughly. You can add a small amount of water to the bottle and shake thoroughly to get all of the toner out of the bottle.
Unlike the Top Coats, the colour for Base Coats is not an accurate match to the swatch, it’s just enough to take it in the right direction before Top Coats are applied.
To loosen the mix, mix thoroughly with a microcement mixer head attachment on a cordless drill. If it still feels stiff, you can add up to 10% water to loosen & mix further. That’s a maximum of 1l per 10kg.
Let the mixture rest for a few minutes before applying.
Applying the Microne Base
Apply the 2nd Coat of Microne Base in exactly the same way as the 1st coat.
Leave to Dry
This should take around 3 hours but may vary depending on temperature and humidity.
Sand with 40/80 Grit Sand Paper
Once the base coats are dry and before you apply your Top Coats, you need to make sure the Base Coats are completely flat. You need to use a strong sand paper, like Silicone Carbide, to prevent colour from the disc transfering to your work.
Flatten the Microne Base with a 40 or 80 grit sand paper. An orbital sander is ideal, but, for smaller areas, you can do it by hand.
Use the sand paper to remove ridges and drips that have dried in the microcement.
The top coats are very thin so any ridges or imperfections in the base coats will be visible in the top coats. Take your time to get it completely flat before moving on to the next step.
Vacuum the surface to remove all dust and debris. Do not wet the microcement.
Microcement Sanding Discs are available from Relentless Microcement.
Mixing 1st Coat of Microne Plus Base with Colour
Add 1 x colour toner for Microne Base to the tub and mix thoroughly. You can add a small amount of water to the bottle and shake thoroughly to get all of the toner out of the bottle.
Unlike the Top Coats, the colour for Base Coats is not an accurate match to the swatch, it’s just enough to take it in the right direction before Top Coats are applied.
And it’s not always essential that you add colour to the 1st base coat, but we have included it incase your order requires a tub to be split between the 1st and 2nd base coat.
Add 500ml Microne Plus Comp B to 10kg Microne Base with Colour and mix well. Once mixed, you’ll have 2 hours working time, so only mix what you need and make sure you’re ready to apply it straight away.
Applying the 1st Coat of Microne Base Plus
Using a Microcement Trowel, work your way out from one corner creating a random edge pattern. Keep trowel movements small and random, avoid long sweeping arches – as these will show through to your final finish.
Use the grain in the microcement as your level – if you apply the microcement thicker than the size of the grain, the finish won’t be as strong and will require a lot more sanding. Run the trowel back over each section that you have put down to smooth it out and remove excess product. You should still be able to see the mesh after after applying this coat.
Completely coat each surface without stopping. For complete rooms, start with ceilings, then walls from left to right (or right to left) and then the floor.
Run your finger or a corner trowel along internal corners to push the microcement into the corner and then gently trowel away the excess product.
Mixing 2nd Coat of Microne Base Plus
Add 1 x colour toner for Microne Base to the tub and mix thoroughly. You can add a small amount of water to the bottle and shake thoroughly to get all of the toner out of the bottle.
Add 500ml Microne Plus Comp B to 10kg Microne Base with Colour and mix well.
Unlike the Top Coats, the colour for Base Coats is not an accurate match to the swatch, it’s just enough to take it in the right direction before Top Coats are applied.
Let the mixture rest for a few minutes before applying.
Applying the Microne Base Plus
Apply the 2nd Coat of Microne Base Plus in exactly the same way as the 1st coat.
Leave to Dry
This should take around 3 hours but may vary depending on temperature and humidity.
Sand with 40/80 Grit Sand Paper
Once the base coats are dry and before you apply your Top Coats, you need to make sure the Base Coats are completely flat. You need to use a strong sand paper, like Silicone Carbide, to prevent colour from the disc transfering to your work.
Flatten the Microne Base with a 40 or 80 grit sand paper. An orbital sander is ideal, but, for smaller areas, you can do it by hand.
Use the sand paper to remove ridges and drips that have dried in the microcement.
The top coats are very thin so any ridges or imperfections in the base coats will be visible in the top coats. Take your time to get it completely flat before moving on to the next step.
Vacuum the surface to remove all dust and debris. Do not wet the microcement.
Microcement Sanding Discs are available from Relentless Microcement.
Cemher Microne Base
Process Apply 2 Coat Microne Base Mix Ratio Pre-mixed in tub
Maximum 10% water to loosenStandard Consumption 20kg per 10m2 Estimated Drying Time Between Coats:
Minimum 3 hours
No Maximum
Before Sealers:
Minimum 12 hours
No MaximumTools Required Microcement Trowel
Microcement Mixer
PPECemher Microne Plus Base
Process Apply 2 Coat Microne Base Plus Mix Ratio 10kg Microne: 500ml Microne Plus Comp B Standard Consumption 20kg per 10m2 Estimated Drying Time Between Coats:
Minimum 3 hours
No Maximum
Before Sealers:
Minimum 12 hours
No MaximumTools Required Microcement Trowel
Microcement Mixer
PPE -
Top Coats
Mixing the 1st Coat Microne Medium with Glass Crystals
You will need 10kg of Microne Medium with Crystals to complete 1 coat over 10m2.
Mix the Microne thoroughly to ensure an even distribution of colour.
Then add 1kg Glass Crystals to 10kg Microne Medium & mix gently on a slow speed. Take care not to mix too aggressively as this could cause the Crystals to break down.
Applying the 1st Coat Microne Medium with Crystals
Use a Microcement Trowel and hold hold it quite flat to the surface. Don’t put as much pressure on as you did with the base coats to avoid the crystals leaving drag marks across the surface.
Gently spread the crystals across the area so that you have full coverage and drag marks are minimised.
Leave to Dry
Leave the Microcement to dry. With crystals in the mix, this often takes more time than standard Microcement. Allow up to 12 hours. Drying times do vary depending on temperature and ventilation.
Mixing 2nd Coat Microne Medium
You will need 5kg per 10m2 for your final Microne Medium.
Mix thoroughly to ensure the colour is well distrbuted.
Do not add glass crystals.
Let the mixture rest for a few minutes before applying.
Applying 2nd Coat Microne Medium
Use this coat to glide over the previous one, filling in any imperfections as you go. Because there’s no crystals in it, you go can a lot thinner with this coat.
Leave to Dry
The microcement needs to be fully dry before sealer is applied. If not the microcement will not reach full hardness and could de-laminate.
Moisture content should be less than 5% before sealer is applied.
The timings below are for guidance only, your microcement may take longer to dry depending on temperature and humidity.
Leave to dry for at least 12 hours.
Sand with 40, 80 & 120 Grit Silicone Carbide Sand Paper
Sand with 40 grit sand paper to reveal the crystals in the microcement. This will be a lot easier with an orbital sander than by hand.
Once you have revealed a good, even spread of crystals, move onto the 80 grit sand paper and give the whole area another sand.
Finally, use a 120 grit sand paper to tidy up your wark and close in the pours.
Vacuum the surface to remove all dust and debris. Do not wet the microcement.
We stock a range of Microcement Sanding Discs on our website.
Mixing the 1st Coat of Microne Medium with Glass Crystals
Microne Medium is pre-mixed with the colour in the tub, all you need to do is give it a mix before you start to loosen it and make sure the colour is evenly distributed.
Then add Microne Plus Comp B to the Microne Medium at a ratio of 500ml Microne Plus Comp B : 10kg Microne Medium and mix well.
Finally, add 1kg Glass Crystals & mix gently on a slow speed. Take care not to mix too aggressively as this could cause the Terrazzo flakes to break down.
You will need 10kg of Microne Medium with Glass Crystals to complete 1 coat over 10m2.
Applying the 1st Coat Microne Medium with Crystals
Use a Microcement Trowel and hold hold it quite flat to the surface. Don’t put as much pressure on as you did with the base coats to avoid the crystals leaving drag marks across the surface.
Gently spread the crystals across the area so that you have full coverage and drag marks are minimised.
Leave to Dry
Leave the Microcement to dry. With crystals in the mix, this often takes more time than standard Microcement. Allow up to 12 hours. Drying times do vary depending on temperature and ventilation.
Mixing 2nd Coat Microne Medium
The microcement is pre-mixed and the colour has been added to the tub, so all you need to do is give it a good mix to Tensure the colour is evenly distributed. hen add 500g Microne Plus to 10kg Tub of Microne & mix well with a microcement mixer. That’s a mix ratio of 1:20.
Once the Microne Plus has been added to the tub, you’ll have around 2 hours working time, so only mix it when you’re ready to use it. And mix in batches if you have a large area.
Do not add Glass Crystals to this mix.
Applying 2nd Coat Microne Medium
Use this coat to glide over the previous one, filling in any imperfections as you go. Because there’s no crystals in it, you go can a lot thinner with this coat.
Leave to Dry
The microcement needs to be fully dry before sealer is applied. If not the microcement will not reach full hardness and could de-laminate.
Moisture content should be less than 5% before sealer is applied.
The timings below are for guidance only, your microcement may take longer to dry depending on temperature and humidity.
Leave to dry for at least 12 hours.
Sand with 40, 80 & 120 Grit Silicone Carbide Sand Paper
Sand with 40 grit sand paper to reveal the crystals in the microcement. This will be a lot easier with an orbital sander than by hand.
Once you have revealed a good, even spread of crystals, move onto the 80 grit sand paper and give the whole area another sand.
Finally, use a 120 grit sand paper to tidy up your wark and close in the pours.
Vacuum the surface to remove all dust and debris. Do not wet the microcement.
We stock a range of Microcement Sanding Discs on our website.
Cemher Microne Medium Sparkle Effect
Process Apply 1 Coat Microne Medium with Glass Crystals, followed by a coat of Microne Medium without Crystals Mix Ratio 10kg Microne Medium Continuous : 1kg Glass Crystals Standard Consumption 10kg per 10m2 Estimated Drying Time Between Coats:
Minimum 3 hours
No Maximum
Before Sealers:
Minimum 24 hours
No MaximumTools Required Microcement Trowel
Microcement Mixer
Silicone Carbide Sanding Discs
Clean Mixing Bucket
Weighing Scales
Measuring Jug
PPEMicrone Plus Medium Sparkle Effect
Process Apply 1 Coat Microne Plus Medium with Glass Crystals, followed by a coat of Microne Plus Medium without Crystals Mix Ratio 10kg Microne: 500ml Microne Plus Comp B : 1kg Glass Crystals Standard Consumption 10kg per 10m2 Estimated Drying Time Between Coats:
Minimum 3 hours
No Maximum
Before Sealers:
Minimum 24 hours
No Maximum
Before Sealers:
Minimum 12 hours
No MaximumTools Required Microcement Trowel
Microcement Mixer
PPE -
Sealers
Mixing 1st Coat AquaMax Pro Walls
Mix the AquaMax Pro Comp A with the AquaMax Pro Walls Comp B in a mixing jug and stir gently with a paint stirrer for at least a minute. Do not whisk as it will put too much air in the mix. Leave to rest for a couple of minutes before applying.
For each coat, you will need 500ml AquaMax Pro Comp A + 50ml AquaMax Pro Walls Comp B per 10m2.
The mixing ratio is 10 x AquaMax Pro Comp A : 1 x AquaMax Pro Walls Comp B.
Only mix enough for 1 coat at a time, as the mixture will only last for 45 minutes once combined.
Applying the 1st Coat AquaMax Pro Walls
Use a medium pile roller to apply the AquaMax Pro evenly across the entire area.
Starting in one corner, apply the AquaMax Pro in an area and then go back over it very gently with the roller to remove any excess product, air bubbles and lines.
Work quickly & randomly keeping the edge wet.
Ensure you cover the full area with AquaMax Pro and use the full amount provided (500ml+50ml per 10m2 for each coat).
Leave to Dry
Leave the 1st coat to dry for a minimum of 12 hours before applying the 2nd coat.
Applying the 2nd Coat AquaMax Pro Walls
After 12 hours, you can complete the 2nd coat of AquaMax Pro. Check the surface for bits of dust and debris that may have settled in it. You can use a 400 grit sanding disc or razor scraper to remove these before applying your final coat.
Mix and apply the 2nd coat in exactly the same way that you did the 1st one.
Again, you will need 500ml AquaMax Pro Comp A & 50ml AquaMax Pro Walls Comp B to complete 1 coat over 10m2.
Leave to Dry
Leave for at least 48 hours. Light use only for the first 14 days.
IMPORTANT: Like all cementitious products, microcement takes 28 days to full harden. It’s at it’s softest for the first 14 days after laying. During this time it should only be subjected to light use and light foot traffic.
Any heavy work is not recommended, but if it does take place then we recommend that you cover the floor with a breathable material or only cover down whilst working & lift the protection off for the majority of the time. The surface needs to dry out and harden. If airflow is restricted, it will stain & not cure correctly.
Mixing MaxiPur
Mix the MaxiPur Comp A with the MaxiPur Comp B in a mixing jug and stir gently with a paint stirrer for at least a minute. Do not whisk as it will put too much air in the mix. Leave to rest for a couple of minutes before applying.
For each coat, you will need 400ml MaxiPur Comp A + 200ml MaxiPur Comp B per 10m2.
The mixing ratio is 2 x MaxiPur Comp A : 1 x MaxiPur Comp B.
Only mix enough for 1 coat at a time, as the mixture will only last for 45 minutes once combined.
IMPORTANT: Eye Protection, Gloves, Filtering Masks, suitable for use with Solvents must be worn when working with MaxiPur
Applying the 1st Coat MaxiPur
Use a medium pile roller to apply the MaxiPur evenly across the entire area.
Starting in one corner, apply the MaxiPur in an area and then go back over it very gently with the roller to remove any excess product, air bubbles and lines.
Work quickly & randomly keeping the edge wet.
Ensure you cover the full area with MaxiPur and use the full amount provided.
Swimming Pools & Outdoor Surfaces
Only apply 1 coat of MaxiPur on Swimming Pools and Outdoor Surfaces, this will allow the Microcement to remain semi-permiable and prevent moisture from building up on the underside.
Leave to Dry
Leave the 1st coat to dry for a minimum of 12 hours before applying the 2nd coat.
Applying the 2nd Coat MaxiPur
After 12 hours, you can complete the 2nd coat of MaxiPur. Check the surface for bits of dust and debris that may have settled in it. You can use a 400 grit sanding disc or razor scraper to remove these before applying your final coat.
Mix and apply the 2nd coat in exactly the same way that you did the 1st one.
Again, you will need 400ml MaxiPur Comp A & 200ml MaxiPur Comp B to complete 1 coat over 10m2.
Leave to Dry
Leave for at least 48 hours. Light use only for the first 14 days.
IMPORTANT: Like all cementitious products, microcement takes 28 days to full harden. It’s at it’s softest for the first 14 days after laying. During this time it should only be subjected to light use and light foot traffic.
Any heavy work is not recommended, but if it does take place then we recommend that you cover the floor with a breathable material or only cover down whilst working & lift the protection off for the majority of the time. The surface needs to dry out and harden. If airflow is restricted, it will stain & not cure correctly.
Cemher AquaMax Pro for Walls
Process Apply 2 Coats of AquaMax Pro for Walls Mix Ratio 10 AquaMax Pro Comp A : 1 AquaMax Pro Comp B
1l AquaMax Pro Comp A : 100ml AquaMax Pro Comp BStandard Consumption 1l per 10m2 Estimated Drying Time Minimum 24 hours between coats
48 hours before light foot trafficTools Required Medium Microfibre Roller
Roller Tray
PPECemher MaxiPur 50
Internal Surfaces Swimming Pools & External Surfaces Process Internal Surfaces: Apply 2 Coats of MaxiPur 50% Swimming Pools & External Surfaces: Apply 1 Coat of MaxiPur 50% Mix Ratio Internal Surfaces: 2 MaxiPur Comp A : 1 MaxiPur Comp B
1l MaxiPur Comp A : 500ml MaxiPur Comp BSwimming Pools & External Surfaces: 2 MaxiPur Comp A : 1 MaxiPur Comp B
1l MaxiPur Comp A : 500ml MaxiPur Comp BStandard Consumption Internal Surfaces: 1l per 8 - 10m2 Swimming Pools & External Surfaces: 1l per 8 - 10m2 Estimated Drying Time Internal Surfaces: Minimum 12 hours between coats
48 hours before light foot trafficSwimming Pools & External Surfaces: 48 hours before light foot traffic Tools Required Internal Surfaces: Roller Suitable for Use with Solvents
Roller Tray
Protective goggles
Rubber gloves
Filtered mask for organic solventsSwimming Pools & External Surfaces: Roller Suitable for Use with Solvents
Roller Tray
Protective goggles
Rubber gloves
Filtered mask for organic solvents -
After Care
Light Use After 48 Hours
You can start to use the microcement surface 48 hours after the final sealer has been applied. By this time, the microcement is sufficiently waterproof, so you can use showers & taps.
You can also install fittings, but its important that you follow the guidance outlined below, for the first 14 days.
First 14 Days
Like all cementitious products, microcement takes 28 days to full harden. Which means it’s at it’s softest for the first 14 days after laying. It also needs to be kep well ventilated so that air can freely flow from the microcement into the atmosphere as it cures.
During this time it should only be subjected to light use and light foot traffic. And no part of the microcement should be covered over. So no leaving bottles in shower areas or rugs on floors.
Heavy work is not recommended during this time, but if it does take place then we recommend covering the floor with a breathable material and only covering down whilst work is taking place. Protection should lifted off for the majority of the time and certainly through the night. The surface needs to dry out and harden. If airflow is restricted, it could stain permanently & not cure to full strength.
Fixing to Microcement Surfaces
Microcement can be drilled and screwed into using bits that are suitable for the substrate. Any holes or cuts will need protecting from moisture penetration by either putting silicone into screw holes or by surrounding fixtures & fitting entirely with silicone. Use 100% pure silicone for this job, to ensure good adherance to the sealed microcement.
Care must also be taken not to scratch the sealers whilst installing fixtures & fittings.
No Dragging or Dropping
Dragging heavy objects over the surface, or dropping them onto the surface is not recommended at any time, as damage could occur. Lift furniture rather than dragging it, and use lids or felt pads to protect flooring from pressure points or abbrasive surfaces.
Microcement is strong, but due to its limited thickness, it will deform in the event of a strong blow if the support beneath deforms. Generally, abrasion and impact resistance is comparable with hard wood.
Stain Resistance
Chemical resistance depends on the sealer used to protect the product. Our sealers are among the best in the industry for both hardness & strength.
Products containing dyes & acidic or alkaline products like tumeric, vinegar, lemon juice or bleach, may leave slight marks on microcement if left on the surface for prolonged time. If cleaning is done quickly, they shouldn’t stain.
If water stains appear at any time, let the stain dry out & reseal immediately. Stains may become permanent if not treated quickly.
Prolongued Exposure to Water
If water is trapped against the surface for a prolonged length of time it may stain & potentially cause the microcement to blister. It is not advisable to leave wet towels, plant pots, wet shampoo bottles etc. in direct, prolongued contact with the microcement.
Cleaning
Microcement surfaces can be cleaned with any pH neutral cleaning products.
Do not clean microcement surfaces with aggressive or descaling products, such as those which contain chlorine, bleach and ammonia as they can damage the sealers.
Aftercare
Use Cemher Floor Protect every 2 -3 months to protect you microcement and to help build up the sealers. This specially designed product is formulated to maintain and protect microcement surfaces by waterproofing, reviving, and safeguarding previously sealed areas. It effectively restores minor scratches in floors without the use of wax, ensuring that the surface remains scratch-free when walked on.
To use, simply dilute 100ml of the product in 7 liters of water and apply it with a mop or cloth. For optimal results, repeat the application every 2 to 3 months.
Fail to Prepare, Prepare to Fail
Surface prep is the most important part of any job. And because microcement is only 3-4mm finished, it’s more important than ever. But don’t worry, we’ve got you covered. Check out our Surface Prep for detailed guidance on preparing a wide range of surfaces for the microcement application.
Surface Prep
Need Help with your Kit?
Installation issues can happen, but we’re here to help. Our comprehensive troubleshooting guides cover common challenges and proven solutions for microcement application.
View Troubleshooting Guides