Applying AquaMax Pro Floors

Follow the directions below to apply the AquaMax Pro for Floors.  AquaMax Pro is a 2-Part product. Once mixed with the AquaMax Pro Floors Comp B, you will have 45 minute working time.

Standard consumption for AquaMax Pro for Floors is 1l Comp A + 200ml Comp B for 2 coats over 10m2.

You will need a medium pile microfibre roller and tray plus a clean mixing bucket and measuring jug.

Mixing 1st Coat AquaMax Pro Floors

Mix the AquaMax Pro Comp A with the AquaMax Pro Floors Comp B in a mixing jug and stir gently with a paint stirrer for at least a minute.  Do not whisk as it will put too much air in the mix. Leave to rest for a couple of minutes before applying.

For each coat, you will need 500ml AquaMax Pro Comp A + 100ml AquaMax Pro Floors Comp B per 10m2.

The mixing ratio is 5 x AquaMax Pro Comp A : 1 x AquaMax Pro Floors Comp B.

Only mix enough for 1 coat at a time, as the mixture will only last for 45 minutes once combined.

Applying the 1st Coat AquaMax Pro Floors

Use a medium pile roller to apply the AquaMax Pro evenly across the entire area.

Starting in one corner, apply the AquaMax Pro in an area and then go back over it very gently with the roller to remove any excess product, air bubbles and lines.

Work quickly & randomly keeping the edge wet.

Ensure you cover the full area with AquaMax Pro and use the full amount provided (500ml+100ml per 10m2 for each coat).

Leave to Dry

Leave the 1st coat to dry for a minimum of 12 hours before applying the 2nd coat.

Applying the 2nd Coat AquaMax Pro Floors

After 12 hours, you can complete the 2nd coat of AquaMax Pro.  Check the surface for bits of dust and debris that may have settled in it.  You can use a 400 grit sanding disc or razor scraper to remove these before applying your final coat.

Mix and apply the 2nd coat in exactly the same way that you did the 1st one.

Again, you will need 500ml AquaMax Pro Comp A & 100ml AquaMax Pro Floors Comp B to complete 1 coat over 10m2.

Leave to Dry

Leave for at least 48 hours. Light use only for the first 14 days.

IMPORTANT: Like all cementitious products, microcement takes 28 days to full harden. It’s at it’s softest for the first 14 days after laying. During this time it should only be subjected to light use and light foot traffic.

Any heavy work is not recommended, but if it does take place then we recommend that you cover the floor with a breathable material or only cover down whilst working & lift the protection off for the majority of the time. The surface needs to dry out and harden. If airflow is restricted, it will stain & not cure correctly.